City Cement starts the trial run of the second production line today

10/12/2014 Argaam

City Cement Company said in a statement to Tadawul that the trial run of its second production line starts today with a designed capacity of 5500 tons per day.
 

The trial run is expected to last for four months the company said without providing any further information regarding anticipated date for commercial production nor the expected financial effect.


According to Argaam; City Cement signed in June 2012 a contract with Sinoma International Company to build a second production line with a capacity of 1.9m tons of clinker per annum at a total cost of SAR 970.63m.

Comments {{getCommentCount()}}

Be the first to comment

{{Comments.indexOf(comment)+1}}
{{comment.FollowersCount}}
{{comment.CommenterComments}}
loader Train
Sorry: the validity period has ended to comment on this news
Opinions expressed in the comments section do not reflect the views of Argaam. Abusive comments of any kind will be removed. Political or religious commentary will not be tolerated.

Most Read